Data Center Construction Costs Canada 2025: Real Numbers You Need

Data Center Being Built
Let's cut to the chase. Building a data center in Canada in 2025 will cost you between $600 to $1,100 per square foot or $7-12 million per megawatt. But here's what those numbers actually mean for your project.

At HKC Construction, based in Mississauga with over 15 years of commercial construction expertise, we've seen data center projects transform from simple server rooms to complex digital infrastructure. If you're considering a data center project, here's everything you need to know about costs in 2025.

Data Center Facility Cost Calculator

Estimate base building construction costs in Canada (2025)

Calculating your estimate...

Estimated Facility Construction Cost
-
Total Estimated Range (CAD)
Estimated Cost Breakdown
Cost Influencers
Estimated Project Timeline

⚠️ Important Disclaimer:

This is a high-level estimate for the base building construction only (shell, core, site work). This estimate EXCLUDES land purchase, critical power/cooling systems for data halls, server racks, and IT hardware. Timeline is an approximation.

For an accurate quote, please contact our experts.

Get a Precise, Detailed Quote

Our experts will provide a complete cost analysis for your project.

📞 Call (647) 468-6747

Quick Cost Calculator: Data Center Construction Pricing

By Facility Type & Size

Small Edge Data Center (1,000-5,000 sq ft)

  • Total Cost: $600,000 - $5.5 million

  • Per sq ft: $600-$1,100

  • Build Time: 6-9 months

Enterprise Data Center (10,000-50,000 sq ft)

  • Total Cost: $6 million - $55 million

  • Per sq ft: $600-$1,100

  • Build Time: 12-18 months

Colocation Facility (50,000-200,000 sq ft)

  • Total Cost: $30 million - $220 million

  • Per sq ft: $600-$1,100

  • Build Time: 18-24 months

Hyperscale Campus (200,000+ sq ft)

  • Total Cost: $120 million - $1+ billion

  • Per sq ft: $600-$1,100

  • Build Time: 24-36 months

By Tier Level (What You're Really Paying For)

Tier II - Basic Redundancy

  • $600-$800/sq ft

  • 99.671% uptime (28.8 hours downtime/year)

  • Single power path with some redundancy

Tier III - Concurrent Maintainability

  • $800-$1,000/sq ft

  • 99.982% uptime (1.6 hours downtime/year)

  • Multiple power paths, N+1 redundancy

Tier IV - Fault Tolerance

  • $1,000-$1,100+/sq ft

  • 99.995% uptime (26 minutes downtime/year)

  • Fully redundant everything

Where Your Money Actually Goes

Here's the real breakdown of a $10 million data center project:

Electrical Infrastructure (40-45%): $4-4.5 million

  • UPS systems

  • Generators

  • Power distribution

  • Switchgear

Cooling Systems (25-30%): $2.5-3 million

  • CRAC/CRAH units

  • Chillers

  • Cooling towers

  • Piping

Building Shell (20-25%): $2-2.5 million

  • Structure

  • Raised floors

  • Security systems

  • Fire suppression

Land & Site Prep (10-15%): $1-1.5 million

  • Land acquisition

  • Site development

  • Utilities connection

Canadian Market Reality Check for 2025

What's Different in Canada

Power Costs by Province:

  • Quebec: $0.05-0.07/kWh (lowest in North America)

  • Ontario: $0.08-0.12/kWh

  • Alberta: $0.06-0.09/kWh

  • BC: $0.07-0.10/kWh

Construction Labor Rates (2025):

  • Electricians: $85-110/hour

  • HVAC Technicians: $75-95/hour

  • General Labor: $45-65/hour

Lead Times That Will Impact Your Budget:

  • Generators: 52-70 weeks

  • UPS Systems: 40-60 weeks

  • Switchgear: 50-65 weeks

  • Cooling Equipment: 35-50 weeks

How HKC Construction Saves You Money

As a leading commercial construction company in Ontario, HKC Construction brings proven expertise to data center projects. Here's how we help optimize costs:

1. Design-Build Approach

Our comprehensive Design & Build service encompasses obtaining necessary codes and permits, selecting finishes, coordinating trades, and managing projects across commercial and industrial sectors. This integrated approach typically saves 10-15% compared to traditional bid-build methods.

2. Value Engineering

HKC has developed cutting-edge methods to actively manage projects, control costs, and effectively schedule while maximizing value against investments. We identify cost savings without compromising quality or performance.

3. Local Expertise

We collaborate closely with Toronto's top tradespeople, ensuring your project exceeds expectations on time, on budget, with no surprises.

Smart Strategies to Reduce Your Data Center Costs

Consider Brownfield Sites

Converting existing warehouses or industrial buildings can save 15-25% versus greenfield development. We've successfully transformed numerous commercial properties into state-of-the-art data centers.

Phase Your Build

Start with 40% of ultimate capacity and expand as needed. This approach can reduce initial capital by 30-40% while maintaining future scalability.

Optimize Power Density

Design for 10-15 kW per rack initially with infrastructure to support 20+ kW future densities. This "right-sizing" approach prevents overbuilding.

Location Matters

Consider these cost factors by region:

  • Montreal: 20-30% lower construction costs, cheap hydro power

  • Toronto: Premium costs but best connectivity

  • Calgary: Competitive pricing, natural cooling advantages

  • Winnipeg: Lowest land costs, excellent cooling climate

Real Project Examples (2025 Pricing)

20,000 sq ft Tier III Enterprise Data Center - Toronto

  • Construction Cost: $18 million

  • IT Infrastructure: $7 million

  • Total Project: $25 million

  • Cost per sq ft: $1,250

  • Timeline: 16 months

5,000 sq ft Edge Facility - Montreal

  • Construction Cost: $3.5 million

  • IT Infrastructure: $1.5 million

  • Total Project: $5 million

  • Cost per sq ft: $1,000

  • Timeline: 9 months

100,000 sq ft Colocation Center - Calgary

  • Construction Cost: $85 million

  • IT Infrastructure: $35 million

  • Total Project: $120 million

  • Cost per sq ft: $1,200

  • Timeline: 22 months

Critical 2025 Trends Affecting Your Budget

AI-Ready Infrastructure

AI workloads require 30-50 kW per rack density, adding 20-30% to cooling costs but essential for future-proofing.

Sustainability Requirements

  • Solar integration: Adds $50-100/sq ft but reduces OpEx by 15-20%

  • LEED certification: Adds 5-7% to construction costs

  • Heat recovery systems: $30-50/sq ft with 3-5 year ROI

Supply Chain Realities

Order critical equipment NOW. With 40-70 week lead times, delays can add 10-15% to project costs through expediting fees and schedule impacts.

Operating Costs of Data Centers That You Can't Ignore

Annual operating expenses typically run 10-15% of construction costs:

For a $10 million facility:

  • Power: $600,000-800,000/year

  • Cooling: $200,000-300,000/year

  • Maintenance: $150,000-200,000/year

  • Staffing: $300,000-500,000/year

  • Total OpEx: $1.25-1.8 million/year

Why Choose HKC Construction for Your Data Center

Who can build my data centers

Since 2010, we've built a reputation for quality craftsmanship, reliability, and client satisfaction. As a 50% women-owned business, HKC Construction deeply values inclusivity and equal opportunity.

What Sets Us Apart:

Our team has expertise in managing projects of all scales with 100% transparency at every stage. We bring:

  • Full-Service Capabilities: Beyond construction, we provide a full spectrum of services from initial concept to post-construction support.

  • Risk Management: We follow strict safety protocols and comprehensive risk management strategies to keep projects on track with no surprises.

  • Transparent Pricing: We offer free, no-obligation estimates, detailed budgets, and comprehensive due diligence reports.

  • ROI Focus: We provide detailed projections of cost savings, operational improvements, and tax credits to boost your ROI.

Get Your Free Data Center Cost Analysis

Ready to get specific numbers for YOUR data center project? Contact HKC Construction at (905) 565-12204 or visit us at 145 Traders Boulevard E, Units 26/27, Mississauga, ON L4Z 3L3.

What You'll Receive:

  • Detailed cost breakdown for your specific requirements

  • Tier level recommendations based on your needs

  • Phasing options to optimize cash flow

  • Equipment lead time planning

  • Operating cost projections

  • Available incentives and tax credits

Get personalized service from our Business Development expert to guide your project from day one.2

The Bottom Line

Data center construction in 2025 requires significant investment, but with the right partner and approach, it delivers exceptional ROI. Whether you need a small edge facility or a massive hyperscale campus, understanding real costs is step one.

HKC Construction combines national capabilities with local expertise to deliver data centers that meet your needs today and scale for tomorrow. We pride ourselves on being a leading, award-winning, national general contractor.

Don't leave your data center investment to chance. Contact HKC Construction today at (905) 565-1220 for your free consultation and cost analysis.

HKC Construction - Building the Future Together         Commercial | Industrial | Institutional | Design-Build 
145 Traders Blvd E, Units 26/27, Mississauga, ON L4Z 3L3 |Phone: (905) 565-1220 | www.hkcconstruction.com

Next
Next

Celebrating National Construction Appreciation Week